St James Hospital
Service: Refurbishment and Demolition Survey
Location: Portsmouth
Completion date: April 2019
Project Duration: 4 weeks
Refurbishment and Demolition Surveys in Portsmouth
We were instructed by a leading housing developer to undertake an Asbestos Refurbishment and Demolition Survey to a two/three storey former hospital site in Portsmouth, which contained an existing 18th century church. The site was being refurbished, in preparation to be turned into luxury residential properties. St James Hospital was constructed in 1879 and had multiple buildings constructed at different times attached, the scope of our works included our teams surveying and accessing the large subfloor voids beneath the hospital.
Due to access and control of the building, our Refurbishment and Demolition programme spread over a 4-month period and required multiple visits where our surveying team accessed different sections vacated by the NHS.
If you need help and assistance managing asbestos in your Portsmouth property, get in touch. Our team are on hand to answer any questions and offer a free project quote.